MKHAQ CONSTRUCTION PROJECT
This MKHAQ madrasah was built on a 1 acre of private waqf land located at Lot 15283 Jalan Rumbia Batu 8 Kampung Sijangkang Telok Panglima Garang Selangor.

The construction process is divided into 4 phases:

  • The first phase has been completed which involves the construction of 5 vocational workshop units at a cost of RM 520,000.
  • The second phase involves the construction of a 2-storey class building.
  • The third phase involves the construction of 2 blocks of 2-storey buildings for the use of dormitories, canteens and madrasah offices estimated to cost RM 2.3 million.
  • The fourth phase is the preparation of sports fields/courts and other facilities estimated to involve a cost of RM 4.5 million.
PROJECT DEVELOPMENT
Now, the construction of the madrasah is entering the second phase, which is the construction of a 2-storey classroom building. The construction of this phase is estimated to involve a cost of RM 1.6 million.

For current progress reports on the site:

  1. Piling work has been completed 100%
  2. Pile cap concrete work has been completed 100%
  3. Ground beam concrete work has been completed 100%
  4. Floor fill work – 100%
  5. Floor lean concrete work – 100%
  6. Floor concrete work – 100%
  7. Concrete work of lower class building columns overall – 100%
  8. Column concrete work – 100%
  9. 2nd floor concrete work Beam formwork- 60%
  10. Solid waste drain from toilets- 100%

May 2022 physical progress report:

  1. Schedule – 30%
  2. Real – 35%

Laporan kemajuan fizikal 2023 (TERKINI) :

  1. Fasa 2 : Binaan bangunan kelas 2 tingkat ( FASA TERKINI)
    • Pemasangan bumbung – 100%